Transmission Information
Transmission Procedures & Agreements
-
Transmission Interconnection Procedures (includes application form) for applications received prior to 10/1/23
-
grant pud Interconnection technical requirements
-
Current transmission queue
-
Open Access Transmission Tariff (OATT) V1
-
Large Generator Interconnection Procedures V1
-
Large Generator Interconnection Agreement V1
-
Small Generator Interconnection Process V0
-
Small Generator Interconnection Agreement V0
Transmission FAQs
Large Generator Interconnection
Transmission Interconnection & Service
Yes. Grant PUD has prepared an Interconnection Request Checklist outlining the information and requirements needed when submitting an interconnection request.
No. Not under the Large Generator Interconnection Procedures (LGIP). Small generation could be allowed if it falls within the size threshold and criteria under the Small Generator Interconnection Process (SGIP). See SGIP for more information.
The Interconnection Customer is responsible for the facilities between its generation facility and the Point of Interconnection (POI). The interconnection studies will determine any additional facilities or network upgrades required and the associated costs.
Grant PUD cannot provide an estimate of costs to build the line due to various factors including land costs, long lead time items, tariffs, and inflation.
No. Grant PUD is evaluating whether regulations would allow Grant PUD to own interconnection facilities built by another party. If Grant PUD changes this policy in the future, developers will be required to meet all regulations applicable to Grant PUD.
No. Grant PUD does not have a policy that allows retail wheeling directly to customers within our service territory.
Yes. Transmission service is separate from the Large Generator Interconnection Agreement (LGIA) and must be requested through Grant PUD’s Open Access Same-Time Information System (OASIS).
A requested Point of Interconnection (POI) can be either a Grant PUD station or a transmission line.
No. Grant PUD does not provide templates for letters of credit or guarantees, and surety bonds are not accepted.
Power Purchase Agreement (PPA) discussions for the sale of energy to Grant PUD must be handled through Grant PUD’s Merchant function. Transmission function staff cannot participate in these discussions under Grant PUD’s Standards of Conduct (SOC) policy.
We may be able to provide publicly available system information or preliminary guidance to help with site selection. However, available capacity cannot usually be confirmed based on a map or preliminary discussion alone. System conditions can change, and a formal interconnection study may be required to determine the impacts of your specific project. We recommend contacting us before making significant decisions based on an assumed point of interconnection.
If available, a preliminary assessment can provide early information about your proposed project and point of interconnection. It is important to remember that preliminary assessments are typically informational. They do not reserve capacity, establish a queue position, guarantee interconnection, or replace the studies required under the applicable interconnection process.
Yes. Applicants may supply Application, Attachment A and Attachment B data by providing equivalent technical data through original equipment manufacturer data sheets, power-flow models, dynamic models, and equipment specifications. Include reference to supporting document files uploaded via the Secure File Transfer Protocol (SFTP) site. Grant PUD reserves the right to request additional information necessary to complete interconnection studies.
No. Grant PUD’s Transmission Business Services department does not accept, facilitate, or participate in offtake discussions or agreements between a customer, third party, and Grant PUD. For questions related to potential offtake opportunities or agreements please contact The Trading and Commercial Operations department at TradingCommercialOps@gcpud.org. Customers seeking information regarding Grant PUD’s All Source Request for Proposal (RFP) should reach out to GrantPUD.RFP@TEAinc.org.
Battery Energy Storage System (BESS)
No. Grant PUD does not currently offer a service, rate, or policy that allows a stand-alone BESS to be charged directly from Grant PUD's electrical system.
The BESS owner must secure a power supply from a third-party source outside of Grant PUD and obtain the necessary transmission service rights through Grant PUD to deliver that energy to the project's Point of Interconnection (POI).
Potentially. The ability to deliver energy to a BESS project depends on the project's location, the amount of energy requested, and the results of the applicable transmission studies. Grant PUD will evaluate each request through its Cluster Study process.
In some cases, yes. If Grant PUD can readily determine that the requested service cannot be accommodated at the proposed Point of Interconnection (POI), the application may be withdrawn from the Cluster Study process, and applicable study fees will be refunded in accordance with Grant PUD's procedures.
It is possible; however, there is no commitment or guarantee that a BESS charging policy or corresponding rate will be developed or approved before the Cluster Study process concludes.
Contact Transmission Services
Have questions regarding Transmission Services? Complete the form on this page.