Commission workshop recap, 11/17/2026 -- Community outreach effort to raise awareness of life near dams

Grant PUD's Dam Safety Team is working with the county's emergency management agencies to coordinate response efforts in the rare event of a dam emergency and to raise public awareness, commissioners heard at their 11/17/2026 workshop at the Hydro Office Building near Wanapum Dam.

Public and employee safety is the top priority at Grant PUD's Columbia River dams, Priest Rapids and Wanapum.

The Dam Safety Plan establishes protocols for working with emergency responders and to inform area residents of inherent risks, recommended preparedness and how to sign up for emergency alerts. Learn more at www.grantpud.org/river.

The team also reviewed a host of dam-safety projects underway at both dams, including the $59 million Spillway Stability Improvement Project at Priest Rapids Dam, which is well underway.

See the full report on pages 1-10 of the workshop presentation materials.

Commissioners also:

-- Canceled their Dec. 22, 2026 business meeting, given the proximity of the holiday celebrations. Commission workshops will happen, as scheduled on Dec. 8 and 15.

Business meetings are one-monthly meetings when commissioners take action on resolutions, motions and conduct other official business.

The last business meeting of 2026 will be Nov. 24. The next business meeting will be Jan. 12, 2027 at Grant PUD's Ephrata Headquarters.

View commission materials at www.grantpud.org/commission-meetings.

-- Received an update on the Quincy Transmission Expansion Plan (QTEP) a $275.5 million package of transmission and switchyard projects that will increase the electric system's capacity to delivery electricity to the growing Quincy area from the current 370 megawatts to 750 megawatts. The projects will improve system reliability and flexibility for fewer and shorter outages.

For maps, costs, timelines and photos see the full report on pages 12-27 or the workshop presentation materials.

-- Heard quarterly business reports from Shared Services – the department that includes Facilities, Transportation, Security and other services needed by all teams across Grant PUD – and Enterprise Technology.

See the full reports on pages 28-38 and pages 39-49 in the workshop presentation materials. 

×