Grant PUD has developed an online, interactive map that provides prospective large power using customers with a high-level look at whether the Grant PUD electric system could have enough capacity for their new electrical service or generation interconnection.

Grant PUD's Transmission Strategy and Development team created the heat map using the utility's transmission models. It uses color-coded regions and numerical estimates to identify potential transmission capacity in megawatts at each station.

Prospective applicants key in the number of megawatts needed for their business or generation project to see the impact of their request at interconnection points across the service area.

The map provides and initial feasibility screening, based on best-available information. It will be updated quarterly but is not intended to replace the formal study process.

Susan Manville, transmission team director, said transmission capacity is constrained in several areas until the system can be expanded.

Her team is continuing study on how the utility can best invest its resources to expand its transmission backbone, meet future demand and coordinate with efforts across the western region to increase transmission capacity. They plan to have data to share with the commission by December.

The map and other information for inquiring large-power using customers can be found on the webpage for Grant PUD Transmission Services.

See the full report on pages 50-70 of the workshop presentation materials


Proposed 2027 rate increases reviewed

Commissioners hosted a public hearing on proposed 2027 rates Tuesday afternoon, Nov. 10, at Ephrata Headquarters.

Rates & Pricing Manager Jeremy Stewart explained the rate proposal protects residential, small commercial and agriculture customers, also known as core customers, by ensuring industrial customers pay for the cost of their growth.

Under the present rate strategy, core customers have the first right to Grant PUD's lowest cost power generated at Priest Rapids and Wanapum dams while Tier 1 and Tier 2 industrial customers pay for higher-cost power necessary to serve growing loads.

The proposal would create two new High Density Compute rate classes to serve data centers: Rate 20, serving data centers with demand below 10 megawatts will expect to see a 24% rate increase.Rate 21, serving data centers with demand above 10 megawatts should expect a 12.5% rate increase.

Tier 1 customers, including large general service and industrial, will see rate increases from 9.1% to 11.7%. At the same time, core customers will see an average increase of 3.5%. Commissioners are scheduled to vote on the proposed rates package Dec. 15.

A Royal City resident who attended said Grant County is fortunate that earlier generations formed the PUD and built the dams for affordable hydropower and thanked Grant PUD for protecting core customers.

Commissioner Tom Flint closed public comment by noting that Grant PUD no longer has the surplus capacity it once did. Going forward, he said, "Those that create the cost will pay for the cost," protecting the farmers, ranchers and rural residents.

See the full report on pages 8-49 of the workshop presentation materials


Analysis continues into below-target survival rates

Grant PUD's Fish, Wildlife and Water Quality teams continue to analyze why their most recent study produced survival rates well below the 86.49% requirement for yearling Chinook and juvenile steelhead migrating through the utility's Columbia River dams, reservoirs and into the Hanford Reach. Prior studies were above the threshold

The preliminary data showed survival for yearling Chinook at 79.4%. Juvenile steelhead survival was 75%, Tom Dresser, senior manager of Fish, Wildlife and Water Quality, told commissioners. Grant PUD must achieve the survival target as a requirement of its federal license to achieve the No-Net-Impact designation for operation of its Priest Rapids and Wanapum dams, he said.

Over the next couple of months, Grant PUDs Fisheries Scientists will be working collaboratively with the utility's external stakeholders to review data accuracy and try to determine what factors may have influenced lower-than-expected survival.

If survival standards are not achieved, additional mitigation requirements may be necessary and could include additional studies, more frequent study cycles, increased hatchery production, additional contribution into the No-Net-Impact fund and changes in dam operations, Dresser said.

Commissioners expressed support for Dresser and his team and pledged to deliver any additional funding needed to meet the survival standard.

See the full report on pages 82-94 of the workshop presentation materials.

Commissioners also:

-- Heard that the Grant PUD-operated boat launch at the Columbia River-community of Vantage could soon be renamed the Vantage Recreation Area and include a day-use area for visitors.

The utility's Lands Resources team will propose the changes to the Federal Energy Regulatory Commission as part efforts to update its mandated Recreation Resource Management Plan.

The boat launch and proposed day-use area is in Kittitas County. Grant PUD owns and operates the launch and some surrounding property as part of its lands around the Wanapum Dam reservoir.

See the full report on pages 71-81 of the workshop presentation materials.

-- Received two quarterly business reviews. Senior Manager of Environmental Compliance and Land Resources Lorie Butterly said fish survival studies and the Quincy Transmission Expansion Plan will remain priorities in 2027, and that a Recreation Resource Management Plan update is due to the Federal Energy Regulatory Commission (FERC) in April. Senior Manager of the Enterprise Project Management Office Aaron Kuntz reported that project performance measures are below target but trending upward, and the ERP+ Phase 1 execution contract is expected in Q1 2027.

See the full reports on pages 95-113 of the workshop presentation materials.